Key players in the planning of the 2032 Brisbane Olympic and Paralympic Games were given little to no notice the Queensland government was going to scrap the $2.7bn Gabba rebuild and ignore a recommendation to build a $3.4bn Victoria Park inner-city stadium.
An inquiry into how prepared Australia for the Brisbane 2032 Olympic and Paralympic Games will examine how the major event will leave a legacy of sporting infrastructure.
The senate inquiry was launched after former Queensland premier Annastacia Palaszczuk’s decision to dump an independent infrastructure agency to oversee projects for the 2032 Games in favour of keeping it in-house.
‘Bushwhacked’: Shock over Games Gabba plan
The Coalition and Greens are heading the inquiry, which is holding a public hearing in Brisbane on Wednesday.
The special senate inquiry will also examine how and where every taxpayer dollar is being spent on the major event.
Other terms of reference for the inquiry will also address the appropriateness of oversight and accountability measures and the impact on housing affordability.
SURPRISE AT GABBA DECISIONS
Although the Queensland government has backflipped on its decision to rebuild the Gabba Stadium for the Games, the initial decision wasn’t pre-discussed with stakeholders.
Senator Richard Colbeck said the former Coalition government was unaware the state government was looking at the Gabba as an option when it agreed to go 50/50 split on the Olympic bid.
“For me, this project, the Gabba and all of the problems it’s brought with it, is symptomatic of the politics the Queensland government played with the Olympic bid,” the former Morrison Sport Minister said.
“It should not be forgotten that without the commitment of the Commonwealth government to provide a 50/50 funding split, it would not be happening.
“They gave us a list of projects in 2021, that list did not involve the Gabba.
“This is the politics that has been played with this Games bid by the Queensland government all the way through to the detriment of the progress of getting the job done.”
Mr Colbeck said Wednesday’s public hearing had raised “more questions” about the Gabba decision – both before and after it was scrapped – and how the state government went about the planning.
“We were completely bushwhacked by the Queensland government when they announced the decision to put the Gabba on the table for the Olympics and Paralympic Games in 2032,” he said.
QUESTIONS OVER MISSED OPPORTUNITIES
Senator Anne Ruston said the inquiry would be looking at what opportunities are being missed because of delays in construction, despite Brisbane being named a host city in 2021.
“We had a runway into the Olympics and we’ve seem to have squandered that already in terms of time,” Senator Ruston said on Wednesday.
Premier Steven Miles appointed Graham Quirk as the lead of the independent review of Brisbane 2032 Olympic and Paralympic venue infrastructure in January.
The former Brisbane lord mayor conducted a 60-day review of the Games’ legacy in which he recommended a $3.4bn new stadium in inner-city Victoria Park.
His stadium option was put forward to replace the state government’s planned $2.7bn knockdown and rebuild of the Gabba cricket ground.
Ultimately, Mr Miles endorsed a cheaper plan, opting to scrap the government’s original Gabba rebuild plan and instead use existing infrastructure.
Suncorp Stadium will be used for the opening and closing ceremonies and the Queensland Sport and Athletics Centre (QSAC) in Nathan for athletics.
QSAC, then QE2 Stadium, hosted the Commonwealth Games in 1982 and is scheduled to be upgraded ahead of 2032.
Acting on behalf of the IOC, John Coates told the inquiry he was made aware of the state government’s decision to go with the QSAC option when State Development Minister Grace Grace called him on March 15.
Mr Coates said Ms Grace told him the government was planning to reject the Victoria Park option, three days before Mr Quirk’s review was made public.
When asked whether he was aware of a “shadow review” performed by the state government while the Quirk review was under way, Mr Coates said he wasn’t involved in anything related to the government’s decision to select QSAC despite favouring upgrading the facilities.
Mr Coates said the Gabba rebuild wasn’t an “Olympic requirement”, given it would mostly benefit cricket and the AFL.
Mr Coates said the IOC would still have to review the QSAC reconstruction, but that would be done in “close consideration” with the transport department.
“No one will tick off on QSAC unless the satisfactory solution is there for transport, whatever it is going to be for the Olympics … (but) it’s not going to be for the opening and closing ceremonies,” he said.
Mr Quirk said the independent review he led recommended the Victoria Park greenfield site over the Gabba rebuild because it was the “superior option”.
“Even with a full Gabba rebuild, we would not get a tier 1 stadium … competitive with other stadiums in Australia,” he said.
Senator Matt Canavan, who said he was a “conservative and a cricket lover”, said he had concerns the Gabba rebuild would lose its historical legacy.
When asked about whether the Queensland government was too focused on the October state elections than the Olympic legacy, Mr Quirk said he could understand why spending money on the Gabba rebuild or the Victoria Park option would seem as “extravagance when families are doing it tough”.
“Any observer would come to the conclusion that there is a fear of the cost of living crisis we’re living through at the moment is driving decisions that would not normally be made in the case,” Mr Quirk said.
But Mr Quirk said it was important people had something to look forward to and see that their city was evolving.
“Even during the Great Depression, people were looking for hope. They had a racehorse called Phar Lap that they looked to for hope.”
Despite the delays, Mr Quirk told the inquiry he believed while no work had been started in terms of construction, community groups would still be able to enjoy facilities before and after the Games.
“The recommendation all of the facilities will be available for community use whether before the games or after the games, depends on when they’re completed.
“They can have years of use of the facilities prior to the Games.
“We would see significant use of facilities before the Games. Even with the Victoria Park proposal, we would have seen cricket be used before the Games.
“There’s not reason some of those indoor sports centres can’t go out to market pretty soon.”
News Related-
High court unanimously ruled indefinite detention was unlawful while backing preventive regime
-
Cheika set for contract extension as another Wallabies head coaching candidate slips by
-
Analysis-West's de-risking starts to bite China's prospects
-
'Beyond a joke' Labor won't ensure PTSD protections: MP
-
Formula One season driver ratings: Lando Norris shines as Max Verstappen nears perfection
-
Catalina golfer Tony Riches scores Guinness World Record four holes in one on same hole
-
Florida coach Billy Napier fires assistants Sean Spencer, Corey Raymond with expected staff shakeup ahead
-
Rohingyan refugee NZYQ accidentally named in documents published by high court
-
Colorado loses commitments of 2 more high school recruits
-
Queensland Health issues urgent patient safety alert over national bacteria outbreak
-
Townsville Community Pantry 'distressed' by fruit, vegetable waste at Aldi supermarket
-
What Is The Beaver Moon And What Does It Mean For You?
-
Labor senator Pat Dodson to resign from politics due to health issues
-
Hamas releases 11 more hostages, as Israel agrees to extend ceasefire