Uttarakhand Tunnel Collapse LIVE: 20 Metres Dug By Vertical Drilling; Parts of Auger Machine Removed

uttarakhand tunnel collapse live: 20 metres dug by vertical drilling; parts of auger machine removed

Uttarakhand Tunnel Collapse LIVE: 20 Metres Dug By Vertical Drilling; Parts of Auger Machine Removed

Uttarakhand Tunnel Collapse Latest News: Efforts to rescue 41 workers trapped inside the Silkyara under-construction tunnel in Uttarakhand’s Uttarkashi entered the 15th day on Monday. The remaining parts of the auger machine stuck in the rubble were removed today. Manual drilling will now start at the tunnel to prepare an escape passage for the trapped workers. Vertical drilling is also being done to make an escape route for the trapped workers.

Meanwhile, two BRO officials were injured after their SUV was hit by a private bus near the Silkyara tunnel site on Sunday afternoon, police said. The accident occurred just half a kilometre away from the tunnel, when three Border Roads Organisation (BRO) officials were on the way to the site in their official vehicle.

Vertical Drilling Underway

Rescuers are drilling into the hill above the Silkyara-Barkot tunnel and had bored nearly 20 metres on the first day of adopting the new approach on Sunday. Rescue workers have to drill down 86 metres to reach the tunnel.

National Highways and Infrastructure Development Corporation Limited (NHIDCL) managing director Mahmood Ahmed said vertical boring would be over by Thursday if there are no hurdles.

As the drilling progresses, 700-mm wide pipes are being inserted to create an escape passage. A little distance away, a thinner, 200-mm probe is being pushed in. It has reached the 70-metre mark.

Rescuers Working On 5 Evacuation Routes

The vertical approach was one of the at least five options on which preparatory work had begun some days back, as anxiety mounted over the fate of the men trapped in the under-construction tunnel on Uttarakhand’s Char Dham route.

The vertical boring option was picked as the next best alternative after the latest in a series of snags that hit the horizontal drilling operation from the tunnel’s Silkyara-end, where an estimated 60-metre stretch of rubble faced rescue workers.

Uttarkashi Tunnel Collapse Latest Updates

  • A portion of the Silkyara tunnel collapsed on Diwali morning, cutting off the exit of the 41 workers inside. The trapped workers are in a built-up two-kilometre stretch of the tunnel. They are being sent food, medicines and other essentials through a six-inch wide pipe. A communication system has also been set up and families occasionally talk to them.
  • A huge auger drill a corkscrew like-device with a rotary blade at the front-end that is drilling into this stretch of debris got stuck Friday evening, forcing officials to give up on the 25-tonne machine.
  • Individual workers have been entering this incomplete escape passage in which a steel chute has been inserted to cut through and bring the stuck blades and the auger’s shaft out in pieces.
  • Sunday morning, a plasma cutter was airlifted from Hyderabad to supplement the gas cutter. A team from the Defence Research and Development Organisation (DRDO) and Army engineers from the Madras Sappers also reached Silkyara.
  • Only 8.15 metres of the 47 metres of the auger shaft that had been pushed into the debris remained to be cut and removed, officials said.
  • Once the auger is completely extricated, rescuers will adopt another fresh approach – manual drilling to clear the remaining 10 or 12 metre stretch of rubble.
  • One worker would enter the steel chute laid so far and operate the drill, and another man send the debris out through a pulley in a time-consuming operation to be carried out in confined space.
  • Meanwhile, work on other options is also in progress, officials said.
  • From Tuesday, rescue workers will start drilling a 180-metre alternative escape tunnel into the side of the hill. This could take 12-14 days.
  • Officials said drilling is also being carried out from the Barkot-end of the tunnel, and the work has progressed about 10 out of 483 metres. This approach could take up to 40 days of drilling, officials said.
  • At his media briefing in Delhi, NDMA member Lt Gen (retd) Ata Syed Hasnain said the best option remained horizontal drilling under which 47 metres of rubble has already been bored through.
  • Relatives of those trapped inside remained anxious after drilling with the auger machine was abandoned.
  • Union Minister of State for Road Transport and Highways V K Singh also visited the disaster site again on Sunday.
  • Chief Minister Pushkar Singh Dhami met the family of trapped worker Pushkar Singh Eiri at his home in Tanakpur, assuring them everyone will be brought out safely.
News Related

OTHER NEWS

Guru Nanak Jayanti: Rishi Sunak Highlights Punjabi Heritage In Message, Trudeau Extends Greetings

In a greeting from 10 Downing Street on the occasion of Guru Nanak Jayanti, British Prime Minister Rishi Sunak mentioned his Punjabi Indian origin, news agency PTI reported. The 43-year-old ... Read more »

What US easing sanctions on Venezuela, home to world’s largest oil reserves, could mean for India

This report is the second of a three-part series on recent Indian engagement in the Latin American and Caribbean (LAC) region. New Delhi: The US’ decision last month to ease ... Read more »

Rajshri Deshpande dedicates OTT award to innocent lives lost in Gaza, Palestine

Rajshri Deshpande dedicates OTT award to innocent lives lost in Gaza, Palestine Actor and social worker Rajshri Deshpande won the Best Actor, Series (Female) award for Netflix’s ‘Trial By Fire’. ... Read more »

‘Ramchandra Keh Gaye…’: From Jan 1, RSS to Spread Word of God, Ayodhya Inauguration Among 10 Crore People

‘Ramchandra Keh Gaye…’: From Jan 1, RSS to Spread Word of God, Ayodhya Inauguration Among 10 Crore People In its effort to take the Ram Janmabhoomi message to households across ... Read more »

Ace designer Rohit Bal critical, on ventilator: report

Ace designer Rohit Bal critical, on ventilator: report Celebrated fashion designer Rohit Bal is in critical condition and is on ventilator support, HT City reported, quoting sources. He has been ... Read more »

Bengaluru: Traffic Advisory Issued, Parking Restrictions In Place As Samyukta Horata Samiti Holds Protest | Details

Bengaluru: Traffic Advisory Issued, Parking Restrictions In Place As Samyukta Horata Samiti Holds Protest | Details The Bengaluru Traffic Police has issued a traffic advisory for November 27 and 28 ... Read more »

Vistara Flights Diverted Due To Air Congestion At Delhi Airport | DETAILS

vistara flights diverted due to air congestion at delhi airport | details Delhi: Two Vistara flight has been diverted to Lucknow and Jaipur due to bad weather and air congestion ... Read more »
Top List in the World